Milton Wastewater Treatment Works Upgrade Adds 50% Treatment Capacity 

Barhale has secured an £11.4M Severn Trent contract to expand a live Derbyshire treatment works for population growth and improved storm flow resilience.

  www.barhale.co.uk
Milton Wastewater Treatment Works Upgrade Adds 50% Treatment Capacity
Milton Wastewater Treatment Works

Severn Trent Water has awarded Barhale an £11.4M contract to upgrade Milton Wastewater Treatment Works (WwTW) to accommodate projected population growth in south Derbyshire. The civil engineering, infrastructure and tunnelling specialist will increase the works’ hydraulic and treatment capacity by 50%, enabling it to serve a projected population equivalent of 30,000 while maintaining existing final-effluent standards and enhancing storm flow resilience at the facility east of Burton-on-Trent.

Early Contractor Involvement and Off-Site Manufactured Inlet Works
Barhale worked closely with its in-house designer ESL and Severn Trent Water through an extensive early contractor involvement phase to develop the detailed design. The major civil, mechanical and electrical improvements will be delivered while the treatment works remains fully operational. Barhale will install new high-level inlet works incorporating screening, grit removal, flow measurement and flow separation. The new equipment will be manufactured off site by water technology provider EPS Water and then connected to an existing balancing tank and downstream assets.

Stainless Steel Storm Tank Adds 1,135m³ of Storage
A new above-ground stainless steel storm tank, 17m in diameter and 5m high, will provide an additional 1,135m³ of capacity, bringing the total storm-storage volume to 1,782m³, an overall increase of approximately 500m³.

Settlement Tank, Pipework and Control System Upgrades
The primary settlement tanks will be fitted with new desludge pumps, and hydraulic modifications will be made to the raising weirs, diffuser drums and skimmer blades. The outlet pipework will be replaced, and the existing spill tanks will be demolished to make way for a new in-ground humus settlement tank. Barhale will also modify the existing dry wells and convert the works return wet well into a dry well. Channels, pipework, chambers and manholes will be upgraded to accommodate the increased flows and driving head, and new control panels will be installed and integrated with the existing motor control centres. Work is expected to be completed in the third quarter of 2027.

Sean McCormick, Contracts Manager, Barhale said: “Milton is a significant upgrade of a live treatment works, so maintaining performance throughout construction has been central to the design. Our early collaboration with Severn Trent, our in-house designer ESL and other delivery partners has allowed us to plan the new assets around the existing treatment process and maximise off-site manufacture. We will continue to work closely with Severn Trent’s operations team to bring the additional capacity into service with minimal disruption to the live works.”

Nick Moczadlo, Project Manager at Severn Trent said: “It’s great to partner with Barhale on these important improvements at our Milton Waste Treatment Works. Through the early collaboration, we have been able to set out a plan that will help the site keep up with growing demands through population growth, as well as keep the site running to avoid any loss of operational activity.”

Edited by Aishwarya Mambet, Induportals Editor, with AI assistance.